Hoover Dam Professional Tour Guide Presentation
Open in PlaceTube Watch on YouTube
Places in this video
- Hoover Dam ▶ 0:00
The guide presents the dam's construction, explaining how the diversion tunnels were plugged and how the penstocks carry water from Lake Mead to the power plants.
- Lake Mead ▶ 0:00
The reservoir in front of the dam, which first filled in 1941 over about six and a half years and today sits far below the top of the dam.
- Hoover Dam Spillways ▶ 0:00
Two spillways built on either side of the river, set about 27 feet below the top of the dam, tested in 1941 and used for two months in 1983.
- Hoover Dam Diversion Tunnels ▶ 0:16
Four diversion tunnels sealed with 400-foot concrete plugs upstream; the downstream sections remain open and two now house the penstocks.
- Hoover Dam Penstocks ▶ 0:49
Four large steel pipes, two on each side of the river, that carry water from the lake to the power plants, each able to move up to 96,000 gallons per second.
- Hoover Dam Intake Towers ▶ 1:37
Four intake towers where water enters the 30-foot-diameter penstocks near their bases before falling about 250 feet to the generators.
- Hoover Dam Power Plant ▶ 2:41
The power plant at the base of the dam, where water passes through turbines to produce power before returning to the Colorado River.